Plan de trabajo



Work package W1: Organisation and management
Objectives: Ensure effective coordination and collaboration among team members; Ensure a fair and transparent decision-making process; Monitor project progress guaranteeing seamless respect of planned schedule, fulfilment of the overall goals within time budget constraints and take corrective actions if necessary; Organisation of meetings; Innovation-Risk-Financial Management; Project reporting.
Task 1.1:  Project Management
Task 1.2 Technical management
Task 1.3 Project reporting
Task 1.4 Risk management and control
Deliverables 
D1.1 Clippings of the kick-off meeting
D1.2 First annual progress report, specifying important results, evolution, and achievements regarding training and transfer of knowledge
D1.3 Mid-term report, specifying important results, evolution, and achievements regarding battery recycling, HW and SW component designs during the first two years of the project
D1.4 Final report on budget execution, project achievements, major conclusions, future work/collaborations
Work package W2.1: CERBEA Platform Development – Circular Economy Framework
Objectives: In this stage, the functional requirements of the CERBEA circular economy platform are specified and developed. These include the identification of the platform functionalities for long term stakeholder engagement, taking into account the objectives set out in the project.
Task 2.1.1 Research in MTP Functional & Technical requirements
Task 2.1.2 Urban Platform design
T2.1.3 Functional design and results implementation
Deliverables 
D2.1.1 Report for circular economy framework for the recycling of lithium batteries opportunities
D2.1.2 Report concerning programs, models, and strategies of recycling of lithium batteries in urban areas
D2.1.3 Report on the rewards campaign model for the promotion of lithium battery recycling based on BlockChain
D2.1.4 Final report on the design/implementation of the circular economy framework for Li-ion battery recycling
Work package W2.2: CERBEA Platform Development – Battery Validation Platform
Objectives:  To design the mechanisms and infrastructures necessary to facilitate citizen access, ease of use and efficient functionality of the innovative CERBEA battery validation platform in the urban environments. Key technologies include the design of an IoT sensorisation platform that will include artificial intelligence for battery health testing. For an optimal and agile measurement, it will be necessary to develop a proprietary hardware device in charge of massively validating a large number of batteries at the same time. Also, this work package includes planning physical battery drop-off and recovery stations to receive, evaluate, recondition and reuse Li-ion batteries, feeding the needs of the accumulator units for a truly effective circular economy framework.
Task 2.2.1 Design of infrastructure to receive discarded batteries
Task 2.2.2 Design & develop IoT battery testing platform
Task 2.2.3 IoT Platform optimization and multisource connectivity
Task 2.2.4 Platform scaleup and upgrade
Task 2.2.5 AI training
Deliverables
D2.2.1 City agreed guidelines for the Li-ion Battery Recovery Infrastructure
D2.2.2 Report on IoT sensorisation platform connectivity & cloud infrastructure architecture
D2.2.3 AI training guidelines
Work package W2.3: CERBEA Platform Development – Manufacture of domestic energy Accumulator unit
Objectives:  CERBEA will define, design and test customized components for the accumulator unit. In this sense, WP2.3 aims to design all the corresponding hardware and software subsystems to manufacture a functional accumulator prototype.
Task 2.3.1 Define accumulators device requirements
Task 2.3.2 Development of software components
Task 2.3.3 Development of hardware components
Task 2.3.4 Production of accumulator prototype
Deliverables
D2.3.1 Requirements specification report
D2.3.2 Accumulator component design and manufacturing report
Work package W3: Demonstration and Validation
Objectives: Demonstration of CERBEA framework functionality using the subsystems researched & developed in WP2.1, WP2.2 & WP2.3. Subsystems will be integrated to develop case study & allow visualizing progress made. The integration, validation & testing activities will allow an iterative, constant, incremental development. In this way, possible deficiencies and improvements to be incorporated in the iterative process of system can be assessed. The final system will integrate software, hardware, networks, devices & monitoring system, to work as a whole.
Task 3.1 Pilot plan
Task 3.2 System Integration & Validation
Task 3.3 Pilot execution
Task 3.4 Cost-Benefit analysis
Deliverables 
D3.1 Pilot Plan and integration guidelines
D3.2 Report of pilot demonstration
D3.3 Cost-benefit analysis of integration of energy storage devices-report
Work package W4: Dissemination and Exploitation
Objectives:  Primary goal is to exploit and disseminate the CERBEA results to a wide audience and increase visibility, to attract new broader cross-sectoral collaborations with urban stakeholders around the world and after project’s end to help propel the project’s innovations to reach the marketplace for maximum impact.
Task 4.1 Dissemination and Exploitation
Task 4.2 Communication
Task 4.3 IPR
Deliverables
D4.1   Project Website Launch
D4.2   Plan for Exploitation and Dissemination strategy including communication activities
D4.3   Launch of Co-creation urban laboratory social platform
D4.4   Workshop-1 proceedings
D4.5   CERBEA publication list by year-2
D4.6   Workshop-2 proceedings
D4.7   Clipping of online and offline news and activity concerning CERBEA
D4.8   CERBEA publication list by year-3
D4.9   Accumulators distribution strategy plan
D4.10 Updated Plan for Exploitation and Dissemination strategy including communication activities
D4.11 Dissemination and transfer of knowledge impact Assessment